Question 1
A slab plan shows a 30 ft by 24 ft slab, 4 inches thick, with an integral 10 ft by 8 ft equipment pad that is 10 inches thick overall. The pad is entirely within the slab footprint, and their top surfaces are flush. There are no openings or other thickened areas. Include 5% waste and round the order up to the next 0.25 cubic yard. How much concrete should be ordered?
Show answer & explanation
Correct answer: C - 11.00 cubic yards